Britain delays major rail project HS2 as costs soar again
Adds Labour reaction
LONDON, March 9 (Reuters) -Britain said on Thursday it would delay building parts of a new high-speed railway linking London and northern England after the cost of the massive project, known as HS2, soared yet again.
In the latest blow to a project designed to modernise Britain's rail network and add capacity on busy tracks, the government said construction of a section in central England would be pushed back.
"We have seen significant inflationary pressure and increased project costs," British transport secretary Mark Harper said in a written statement to parliament.
Companies involved in building HS2 include Kier Group KIE.L, Balfour Beatty BALF.L and Vinci SGEF.PA.
First proposed in 2009, HS2 is billed as the largest infrastructure project in Europe and aims to help the UK catch up with other European countries with extensive high-speed rail.
The whole project, which will connect London Euston to Manchester, had been scheduled for final completion from 2035-2040.
But Harper said the section between the city of Birmingham and the town of Crewe around 60 miles to its north would be "rephased" by two years. He did not set a new completion date for the whole northern section linking Birmingham to Manchester.
He also said the section of rail linking HS2 to Euston station in central London would be deprioritised, with work focusing first on joining the line up to a newly-built but much less central hub in suburban north-west London.
"These are the difficult but responsible decisions we are taking, that put the priorities of the British people first, in controlling inflation and reducing government debt," Harper said.
HS2 was expected to cost between 72 billion and 98 billion pounds at 2019 prices, but since then the bill has been pushed up by inflation - which ran at around 18% in the construction industry last year, affecting materials like timber, steel and concrete.
The 2019 budget was already a big jump from the 2015 estimate of 56 billion pounds. The project has also already been scaled back; in 2021 the government scrapped a planned link to Leeds, citing spiralling costs.
"Tens of thousands of jobs, and billions in economic growth are dependent on this project," said Louise Haigh, transport policy chief for Britain's opposition Labour Party. The government's "chaos and chronic indecision" was holding back jobs, growth and costing taxpayers, she added.
Construction of the first part of HS2, from west London to Birmingham, is already underway.
Reporting by Sarah Young and Sachin Ravikumar; editing by William James
면책조항: XM Group 회사는 체결 전용 서비스와 온라인 거래 플랫폼에 대한 접근을 제공하여, 개인이 웹사이트에서 또는 웹사이트를 통해 이용 가능한 콘텐츠를 보거나 사용할 수 있도록 허용합니다. 이에 대해 변경하거나 확장할 의도는 없습니다. 이러한 접근 및 사용에는 다음 사항이 항상 적용됩니다: (i) 이용 약관, (ii) 위험 경고, (iii) 완전 면책조항. 따라서, 이러한 콘텐츠는 일반적인 정보에 불과합니다. 특히, 온라인 거래 플랫폼의 콘텐츠는 금융 시장에서의 거래에 대한 권유나 제안이 아닙니다. 금융 시장에서의 거래는 자본에 상당한 위험을 수반합니다.
온라인 거래 플랫폼에 공개된 모든 자료는 교육/정보 목적으로만 제공되며, 금융, 투자세 또는 거래 조언 및 권고, 거래 가격 기록, 금융 상품 또는 원치 않는 금융 프로모션의 거래 제안 또는 권유를 포함하지 않으며, 포함해서도 안됩니다.
이 웹사이트에 포함된 모든 의견, 뉴스, 리서치, 분석, 가격, 기타 정보 또는 제3자 사이트에 대한 링크와 같이 XM이 준비하는 콘텐츠 뿐만 아니라, 제3자 콘텐츠는 일반 시장 논평으로서 "현재" 기준으로 제공되며, 투자 조언으로 여겨지지 않습니다. 모든 콘텐츠가 투자 리서치로 해석되는 경우, 투자 리서치의 독립성을 촉진하기 위해 고안된 법적 요건에 따라 콘텐츠가 의도되지 않았으며, 준비되지 않았다는 점을 인지하고 동의해야 합니다. 따라서, 관련 법률 및 규정에 따른 마케팅 커뮤니케이션이라고 간주됩니다. 여기에서 접근할 수 있는 앞서 언급한 정보에 대한 비독립 투자 리서치 및 위험 경고 알림을 읽고, 이해하시기 바랍니다.