Canadian regulators approve preliminary interim tolls on expanded Trans Mountain pipeline



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Canadian regulators approve preliminary interim tolls on expanded Trans Mountain pipeline</title></head><body>

Adds details on toll dispute, analyst quote

By Nia Williams

Nov 30 (Reuters) -The Canada Energy Regulator (CER) on Thursday approved preliminary interim tolls for the expanded Trans Mountain pipeline system, allowing the project to begin charging for shipping services once operations start.

The interim benchmark toll is set at $11.46 per barrel and applies to shippers with a 15-year contract transporting under 75,000 barrels per day (bpd) from Edmonton to Burnaby. Other tolls will vary by path, length of contract and volume commitment, the CER said.

Trans Mountain applied in June for a base toll of $11 to $12 a barrel, depending on the type of crude shipped and its destination, but was met with opposition from a number of contracted shippers including Canadian Natural Resources Ltd CNQ.TO and Cenovus Energy CVE.TO, who argued tolls were too high.

The newly approved interim benchmark toll consists of a fixed amount of $10.88 per barrel and a variable portion of $0.58. The fixed amount is nearly double what Trans Mountain estimated it would be in 2017, as a result of ballooning construction costs.

The 590,000 bpd expansion project will nearly triple the flow of Canadian crude to the Pacific coast, but is expected to cost C$30.9 billion ($22.79 billion), more than four times its original budget.

TMX is scheduled to come online by the end of March 2024.

The CER is still planning to hold ahearing on final tolls next year, and asked Trans Mountain to provide additional cost information by Dec. 15.

Long-term shipping contracts cover 80% of the expansion project's capacity. The final tolls will affect the value of the pipeline when the Canadian government, which bought it in 2018 to ensure the expansion got built, puts it up for sale.

Many analysts expect the government will struggle to recoup its full investment in Trans Mountain. Morningstar analyst Stephen Ellis said discussions around tolls could get more heated if the pipeline is sold before they are finalised.

"Shippers are unlikely to be happy paying tariffs based on a huge cost number when it has just been valued at a lot less," Ellis said.


($1 = 1.3558 Canadian dollars)



Additional reporting by Seher Dareen in Bengaluru; Editing by Maju Samuel, Josie Kao and Deepa Babington

</body></html>

Disclaimer: The XM Group entities provide execution-only service and access to our Online Trading Facility, permitting a person to view and/or use the content available on or via the website, is not intended to change or expand on this, nor does it change or expand on this. Such access and use are always subject to: (i) Terms and Conditions; (ii) Risk Warnings; and (iii) Full Disclaimer. Such content is therefore provided as no more than general information. Particularly, please be aware that the contents of our Online Trading Facility are neither a solicitation, nor an offer to enter any transactions on the financial markets. Trading on any financial market involves a significant level of risk to your capital.

All material published on our Online Trading Facility is intended for educational/informational purposes only, and does not contain – nor should it be considered as containing – financial, investment tax or trading advice and recommendations; or a record of our trading prices; or an offer of, or solicitation for, a transaction in any financial instruments; or unsolicited financial promotions to you.

Any third-party content, as well as content prepared by XM, such as: opinions, news, research, analyses, prices and other information or links to third-party sites contained on this website are provided on an “as-is” basis, as general market commentary, and do not constitute investment advice. To the extent that any content is construed as investment research, you must note and accept that the content was not intended to and has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such, it would be considered as marketing communication under the relevant laws and regulations. Please ensure that you have read and understood our Notification on Non-Independent Investment. Research and Risk Warning concerning the foregoing information, which can be accessed here.

Risk Warning: Your capital is at risk. Leveraged products may not be suitable for everyone. Please consider our Risk Disclosure.